1, Requirement

Participant in the construction of Interior and Exterior works for New of PPCBank _Veng Sreng Branch

Maximum Expected Construction Period: Up to 3 months (from the date of signing contract)


Note:

The construction period can be extended depending on unexpected circumstance on mutual consents with PPCBank.

2, Field descriptions

Reference to the Layout contents with the following details

  • Interior works

    1. BM office (1person)

    2. Deposit Counter (3 tellers, 1 chief teller and extra desk next to chief teller)

    3. Loan office (6 loan officers, 1 chief loan officer)

    4. Vault Room (at least 16 m2)

    5. 2 or 3 Meeting rooms for deposit/loan customers (be flexible based on the actual space)

    6. Pantry room including sink

    7. Toilet (WC) (proper size for the number of working staff)

    8. Level up the floor 30cm

    9. Server room

    10. Electrical room

    11. Storage rooms

  • Note for interior design

    • Submission 3D design at your discretion based on any suggestion to improve branding image

    • For all items mentioned above and any additional works, the contractor responsible for the interior and exterior construction shall propose the design at its discretion and efficiently incorporate it into the layout. Please refer to the current branches’ design and layout for guidance. etc.

    • Counters must face to the entrance door.

    • Submission 3D design at your discretion and suggestion to improve branding.

    • Water proof of any places inside the bank in order to protect all equipment shall be required.

    • Quotation including M&E (Reference to specification of Layout) shall be submitted.

    • Quotation of network and telephone shall be submitted separately by attaching company profile including specific network and telephone, vendor name and contact information.

  • Exterior works

    1. CRM Booth (1 CRM)

    2. Signboard (arrangement is required considering the electric line, it does not have to be the same as the existing signboard created suggestions are required)

    3. Exterior Coverage (it must specify the product origin)

    4. Toilet (WC) for security guards

    5. Parking lot in front the building

    6. Water proof and zinc roof shall be required for any places to protect leaking from raining, in terms of roof with proper water way.

    7. Generator room at proper place including electricity connection works.

    8. Standing pole for promoting bank branding

  • Note for Exterior design

    • Submission 3D design at your discretion based on any suggestion to improve branding image.

    • Note: Please refer to PPCBank design of current branches design.

3, Submission deadline for applications

Tuesday, 10th March 2026 (11:00 AM))

4, How to submit your application
  • Application documents shall be submitted to Administrative Department of PPCBank

  • PPCBank HQ Building Address: Nº 217, Norodom Blvd., Phum 10, Sangkat Tonle Bassac, Khan Chamkarmorn, Phnom Penh, Cambodia

Application documents shall be enclosed with the company seal.

5, Application Documents

Company introduction including such as company name, establishment year, capital, total assets, previous year’s net profit, number of employees, major business field, representative nationality

6, Applicant qualification

Company related to the construction of interior and exterior that registered business in Cambodia

7, Decision-making method of company

Decision is according to the bank’s internal regulations.

8, Application Deposit

None

9, Result notification date

PPCBank will notify on proper date before construction.

10, Signing of contract for construction

Within 10 days from the date of notification of the result

11, What to note when submitting your application
  • Identify guidelines, regulations, special conditions, etc. of local authority in relation to facility construction

  • Inspection procedure will be carried out after completion of construction

If you have any concern, please feel free to contact us.

  • Mr. YUN Chang Ho, Senior Manager (Korean)/ Tel: 012 850 513

  • Mr. PHAN Sovanndos, Administrative Manager (Khmer)/ Tel: 089 669 967