The construction of Interior and Exterior Works for New PPCBank 271 Branch

Published Date: March 27, 2026

1, Requirement

Participant in the construction of Interior and Exterior works for New of PPCBank _271 Branch

Maximum Expected Construction Period: Up to 3 months (from the date of signing contract)


Note:

The construction period can be extended depending on unexpected circumstance on mutual consents with PPCBank.

2, Field descriptions

Reference to the Layout contents with the following details

  • Interior works

    1. BM office (1person)

    2. Deposit Counter (3 tellers, 1 chief teller and extra desk next to chief teller)

    3. Vault Room (at least 16 m2)

    4. 2 or 3 Meeting rooms for deposit/loan customers

    5. 2 Pantry rooms including sinks (8 chair for each room)

    6. Toilet (WC) (proper size for the number of working staff)

    7. Server room

    8. Electrical room

    9. Loan office (6 loan officers, 1 chief loan officer with meeting table)

    10. 2 or 3 Document Storage rooms

    11. Reserve stock

  • Note for interior design

    • All designed layout is designed by contractor as well as flexible and creative idea.

    • For all items mentioned above and any additional works, the contractor responsible for the interior and exterior construction shall propose the design at its discretion and efficiently incorporate it into the layout. Please refer to the current branches’ design and layout for guidance. etc.

    • The wall at ground floor, wall and veranda at mezzanine floor as attached layout shall be demolished.

    • Counters must face to the entrance door.

    • Submission 3D design at your discretion and suggestion to improve branding.

    • Water proof of any places inside the bank in order to protect all equipment shall be required.

    • Quotation including M&E (Reference to specification of Layout) shall be submitted.

    • Quotation of network and telephone shall be submitted separately by attaching company profile including specific network and telephone, vendor name and contact information.

    • The dimensions must be specified and reflected in the submitted designed layout.

  • Exterior works

    1. ATM Booth (2 ATM)

    2. Signboard (arrangement is required considering the electric line, it does not have to be the same as the existing signboard created suggestions are required)

    3. Exterior Coverage (it must specify the product origin)

    4. Water proof and zinc roof shall be required for any places to protect leaking from raining, in terms of roof with proper water way.

    5. Standing pole for promoting bank branding

    6. Parking lot in front the building

    7. Reserve parking and stock (basements)

    8. Generator room at proper place including electricity connection works.

    9. Toilet (WC) for security guards

  • Note for Exterior design

    • Submission 3D design at your discretion based on any suggestion to improve branding image.

    • Note: Please refer to PPCBank design of current branches design: HLM, CMC and SHV

3, Submission deadline for applications

Thursday, 9th April 2026 (2:00 PM)

4, How to submit your application
  • Application documents shall be submitted to Administrative Department of PPCBank

  • PPCBank HQ Building Address: Nº 217, Norodom Blvd., Phum 10, Sangkat Tonle Bassac, Khan Chamkarmorn, Phnom Penh, Cambodia

Application documents shall be enclosed with the company seal.

5, Application Documents

Company introduction including such as company name, establishment year, capital, total assets, previous year’s net profit, number of employees, major business field, representative nationality

6, Applicant qualification

Company related to the construction of interior and exterior that registered business in Cambodia

7, Decision-making method of company

Decision is according to the bank’s internal regulations.

8, Application Deposit

None

9, Result notification date

PPCBank will notify on proper date before construction.

10, Signing of contract for construction

Within 10 days from the date of notification of the result

11, What to note when submitting your application
  • Identify guidelines, regulations, special conditions, etc. of local authority in relation to facility construction

  • Inspection procedure will be carried out after completion of construction

If you have any concern, please feel free to contact us.

  • Mr. YUN Chang Ho, Senior Manager (Korean)/ Tel: 012 850 513

  • Mr. PHAN Sovanndos, Administrative Manager (Khmer)/ Tel: 089 669 967